Sean submitted and Rene accepted a bid to supply approximately 4,000 tons of trap rock for an airport at a unit price. The parties executed a standard form of “Invitation, Bid, and Acceptance (Short From Contract)” supplied by Rene, including typed terms “to be delivered to project as required,” “delivery to start immediately,” and “cancellation by Rene may be effected at any time.” However, _____ requires that Rene orders and accepts the rock within a reasonable time unless Rene has given Sean a notice of intent to cancel.
- (A) good faith 正確答案
- (B) good feeling
- (C) good intent
- (D) good will
官方答案:(A)good faith
詳解
雖約定得隨時取消,誠信原則(good faith)仍要求買方於合理期間內訂購受領,或先通知取消意思。
同章其他題目:111 年
題目與答案照律師司法官第一試綜合法學(二)公司法、保險法、票據法、證券交易法、強制執行法、法學英文官方公開題庫(110-115 版)收錄;詳解是我寫的整理,正式內容以主管機關公告為準。